The new Francis M. Leahy School K-8 is being constructed on the location of the former Leahy School and joins the Oliver project as Lawrence’s first new school building in more than two decades. The 1,000-student school complex will combine the Leahy Elementary, Lawlor and Leonard Middle School under one roof. The City of Lawrence has partnered with the Massachusetts School Building Authority, from which partial grant reimbursement will be received. Construction of the new School is ongoing with anticipated occupancy for the start of the academic year in the fall of 2025.
The roof structures for Stairs 1 and 4 were installed, brickwork on the North wall is complete; the East is underway. Work on the South elevation and roof terrace walls continued throughout the month and is 90% complete. Eversource installed the gas meter and bollards to protect the meter. The HVAC ductwork in the gym is 85% complete. Framing of the exterior walls is 98% complete. Workers continued with the PVC membrane, and curb blocking for the Roof Terrace and expected to be water tight the first week of December. The West elevation window installation was completed. The North elevation window installation was started, beginning on Level 4 and is ongoing.
Leahy November Update Progress Report