Framing of the exterior walls remains 98% complete, with the framing of the openings in the NW corner of the Bruce St. loading zone and the covered parking area ceiling remaining. Installation of the aluminum windows, including sealing of the interior and exterior, was ongoing throughout the month and is 92% complete. Performance testing of the aluminum windows began on February 3rd and continued through the 11th.
Leahy February 2025 Update Progress Report