The brickwork on the West elevation continued through the end of the month. Completing most of the wall, less the North corner, which is being used as the hoisting area for the trades. Brickwork on the North wall is underway working East to West and is approximately 25% complete. Work on the East wall was started at the North corner. Worker installed blocking atop of Courtyard parapet to receive the metal trim and PVC membrane. The Roof Terrace PVC membrane, workers started prepping the roof by installing equipment curbs, roofing AVB and blocking atop of roof edge curb. Click the link below to get a more detailed report on October progress.
Leahy October Update Progress Report