Leahy Construction Updates

Leahy Construction Update June 2024
Traffic interruptions are expected to continue at Erving Ave. and Bruce St. for deliveries during the daytime hours as detailing work continued through the end of the month. Aligning and securing the masonry relieving angles will be ongoing through mid-June.
Leahy June Update Progress Report
- Details
- Hits: 3278

Leahy Construction Update May 2024
Placing the final slab on 2nd floor deck section of concrete.
Leahy May Update Progress Report
- Details
- Hits: 3538

Leahy Construction Update March 2024
Utilities being installed underground.
Leahy March Update Progress Report
- Details
- Hits: 3467

Leahy Construction Update February 2024
Structural steel is progressing and should be completed mid-to-late March.
Leahy February Update Progress Report
- Details
- Hits: 3018

Leahy Construction Update December 2023
The construction team received the first truckload of structural steel.
- Details
- Hits: 2150